ACE Weekly 12/17/04 - 12/23/04 All ACE spacecraft subsystems are performing nominally. ============================================================================ Orbit/Attitude: Maneuvers completed Type Attitude Date 12/20/04 DOY 355 2004 Thrusters 2R 4R+ 4R- Duration 11:15 minutes Start Time 16:52:26z Stop Time 17:03:41z Firing 57 pulses The next attitude maneuver is scheduled for 01/04/05. ============================================================================ OCRs: SWPX 037 Planned - Will coordinate with instrument team after the holidays. The SWEPAM Ion gain is starting to “slip” due to instrument aging. Provisions are made in the instrument to adjust for this loss by increasing the CEM voltage level but the gain is not linear across the entire spectrum. These sensitivity measurements are intended to characterize this non-linear behavior to let the SWEPAM science team determine the optimal CEM voltage to continue operations with and to define compensation parameters for data processing. ============================================================================ Ongoing Activities: ROBOTT ACE transitioned to Lights Out Operations on 11/13/04. All nominal realtime operations are now being performed using ROBOTT, with the exceptions of maneuvers and special commanding. 20 DRs have been written for ROBOTT v0.9. The patch to resolve the premature schedule deletion was installed on 12/21/04. Further testing will be completed when DSN's week 01 schedule is renamed from forecast.w01 to 7dayss.w01 which should occur on 12/30/04. ============================================================================ Extra Activities: None ============================================================================ Anomalies: DOY 352 (12/17/04) ACE Anomaly S04-0021 SIS Temperature Violations SIS_M2BMATRIXBRD and SIS_M1AMATRIXBRD temperatures violated their yellow high limits (YH=39C) due to the spacecraft approaching perihelion, the sun angle increasing to above 10° (spacecraft temperatures generally increase with larger sun angles) and the slow degradation of insulation. The times below give the first violation and also when the values were continuously out of limit. Mnemonic First violation Start Continuous End Continuous SIS_M2BMATRIXBRD 351-22:49:47 352-01:36:11 355-19:03:38 SIS_M1AMATRIXBRD 352-23:55:55 353-02:42:19 355-18:12:26 The attitude maneuver on DOY 355 2004 (12/20/04) reduced the sun angle to 4.8° and the temperatures were no longer in violation. Further violations, however, were expected as the sun angle increased before the next maneuver on DOY 004 2005 (1/4/04). The SIS instrumenters requested the yellow high and red high limits to be increased by 2C. IMPACT: Limits have been increased after instrumenter review. DOY 355 (12/20/04) ACE Anomaly G04-0156 TPOCC State Manager Not Connected While initializing TPOCC manually, TPOCC displays were prematurely started and were unable to contact the ace_stmgr_parser server. TPOCC was terminated and restarted successfully with enough time allowed for initialization. IMPACT: None. ROBOTT is programmed to wait long enough to allow for TPOCC initialization to complete. DOY 356 (12/21/04) ACE Anomaly G04-0157 TPOCC Data Server Not Updated. While running g_end_day.prc, the data server had not updated the telemetry parameters before the procedure reached the telemetry checks. The procedure will be updated to ensure that that TPOCC is given sufficient time to process telemetry before checks are made. IMPACT: None. ROBOTT entered the GO directive and the procedure completed.