ACE Weekly 01/07/05 - 01/13/05 All ACE spacecraft subsystems are performing nominally. ============================================================================ Orbit/Attitude: No maneuvers were executed this reporting period. The next attitude maneuver is scheduled for Friday 01/14/05. ============================================================================ OCRs: DOY 007 (01/07/05) SWPX-037 SWEPAM-I Gain and CEM Voltage Level The CEM voltage level was toggled between Level 0 (current configuration) and Level 2. The measurements will characterize the non-linear Gain for determining the optimal CEM voltage and to define compensation parameters for data processing. The pending CEM Level takes affect at the start of the Normal Cycle as opposed to the start of each MODE. Instrument team is evaluating the data and further measurement options. ============================================================================ Ongoing Activities: None ============================================================================ Extra Activities: None ============================================================================ Anomalies: DOY 008 (01/08/05) ACE Anomaly G05-0002 MAD 26m D66 CMD Mod Index Incorrect CMD MOD Index delayed beginning of activities by 40 minutes. IMPACT: Minimal. All playback data captured. DR M102970 DOY 009 (01/09/05) ACE Anomaly G05-0003 ROBOTT - No Cron Schedule An intermittent timing issue prevents ROBOTT from updating the appropriate schedule files. ROBOTT provides the error message: The pass file (pparm) had old pass schedule (006)(007). Please check. IMPACT: FOT arrived on Sunday to complete activities and update the CRON schedule. DOY 009 (01/09/05) ACE Anomaly G05-0004 GDS 34m D24 Antenna Stopped Antenna stop resulted in 15 minute telemetry outage. Uplink not restored. IMPACT: See AR 0005 and 0006 below. DR G105166 DOY 009 (01/09/05) ACE Anomaly G05-0005 Pages Not Delivered At the beginning of the 15 minute telemetry outage, the paging service stopped delivering messages after 10 messages were sent within 1 minute. Five pages were lost. Pages were again being received 10 minutes later. All notifications were later found to have been successfully received via email. IMPACT: FOT was able to piece together information on the TLM outage from pages that were received. DOY 009 (01/09/05) ACE Anomaly G05-0006 SSR Redumps not completed Since uplink was not restored after the 15 minute telemetry outage, SSR redumps were not performed. ROBOTT did not provide notification (neither pager nor email) that the procedure was not started. IMPACT: Redumps completed manually on Monday. DOY 010 (01/10/05) ACE Anomaly G05-0007 ROBOTT not resumed After manually completing redumps, ROBOTT was not correctly resumed by OE. IMPACT: SSR redumps and final state-of-health checks were not completed. Fortunately, no redumps were needed. DOY 011 (01/11/05) ACE Anomaly G05-0008 GDS 34m D24 Antenna Stow/High Winds Sustained winds at 50 MPH required the station to stow the antenna resulting in a 1hour 10min TLM outage. IMPACT: Remaining SSR Playback was completed on next day. DR G105177 DOY 012 (01/12/05) ACE Anomaly G05-0009 Incorrect DSN Schedule DSN 7-day schedule incorrectly had the Change Log instead of the Activities Listing. ROBOTT correctly flagged the incorrect schedule and continued to use the old schedule. IMPACT: Minimal. Fortunately, schedule changes had been implemented and downloaded before the schedule was replaced with the Change Log. DR N102601 DOY 012 (01/12/05) ACE Anomaly G05-0010 TAPS Data Capture Failed From Friday (01/07/05) to Sunday (01/08/05) TAPS Data Capture Daemon failed. Reboot of both workstations on Monday reinstated the Daemon. IMPACT: Three days of data will be manually ingested. DOY 012 (01/12/05) ACE Anomaly G05-0011 GDS 34m D24 Transmitter Failure Activities delayed 34 minutes due to Transmitter Power Supply problems. IMPACT: SSR Playback from yesterday was successfully completed manually, but the remaining SSR playback for today was completed on Thursday. DR G105185 DOY 012 (01/12/05) ACE Anomaly S05-0001 SSCPAP5V SSCPAP5V briefly violated the Yellow Low limit of 4.25V (2 seconds). Jim Raines notified. IMPACT: Awaiting instructions from Jim Raines if necessary. DOY 012 (01/12/05) ACE Anomaly S05-0002 SSR Plbk During Switch to Low Rate SSR B was in playback mode when the C&DH switched from ADC to RTSW at EOT. The SSR did not transition to Idle and SSR read pointer stopped incrementing. The SSR was manually commanded to idle at the beginning of the next pass on DOY 013. IMPACT: No data affected. Procedures will be rewritten to handle this contingency.