Today the first of 2 Combined Systems Tests (CSTs) was successfully performed. The CST verifies the interfaces between the Observatory, Rocket, Carrier Aircraft and Range and includes functional checkouts of the Rocket and Observatory. This test was completed successfully, pending data review, and will be repeated following the ferry flight out to Kwajalein.
Major Milestone Schedule dates
All days are CONUS
6/3 Combined System Test - Complete
6/5-6 NuSTAR Ferry Flight to Kwaj
6/9 LMCM and Dress Rehearsal
6/11 LRR
6/13 ILC
Thanks,
Garrett